Implementation Timeline
|
Date |
Task |
Description of
Task |
Responsible
Party |
|
Jan 2003 |
Attend assessment meeting or conference call. |
Using the Implementation Guide, school and Apple/PowerSchool will complete an implementation assessment, project overview, and break down roles and responsibilities for each party. |
School and Apple/PowerSchool |
|
Jan 2003 |
Order hardware, and set up network and Internet connection. (Step 1 issues) |
Order required hardware for PowerSchool SIS implementation. (Ensure school's network is operational). Obtain IP address. Review Internet connection requirements. |
School |
|
Feb 2003 |
Prepare for PowerSchool SIS installation. (Step 2 and Step 3) |
Assemble hardware. Install Timbuktu. Request installation of PowerSchool SIS. |
School |
|
Feb 2003 |
Confirm configuration validity. |
School and PowerSchool work through firewall and IP issues
to establish Internet connectivity. |
School and Apple/PowerSchool |
|
Feb 2003 |
Install PowerSchool SIS on server. |
Place product on server. Verify connectivity inside and outside of firewall (for staff and parent access). |
Apple/PowerSchool |
|
Mar 2003 |
Logon to PowerSchool SIS and perform initial setup. (Step 4 and Step 5) |
Create personal logon. Setup other users. Configure system settings. |
School |
|
Mar 2003 |
Enter your School Setup information in PowerSchool SIS. (Step 6) |
Enter information on the School Setup page in PowerSchool SIS. |
School and PowerSchool (as needed) |
|
Apr, May Jun 2003 |
Convert and import data into PowerSchool SIS. (Step 7 and Step 8) |
School is responsible for migrating data from prior system. The Apple/PowerSchool Implementation team will offer assistance (email and phone service) during data conversion process. Online templates are available as a guide for field processing. Data conversion by PowerSchool is offered as a contracted service, provided data is in ASCII tab-delimited format. |
School and Apple/PowerSchool (as needed) |
|
Jul 2003 |
Install PowerGrade and download appropriate manuals. (Step 9) |
Install PowerGrade on training workstations and teacher workstations. |
School |
|
|
Download Adobe Acrobat and supplemental documentation. |
Download Adobe Acrobat and the PowerSchool SIS User's Guide and the PowerGrade Manual. Distribute as needed. Explore the PowerSchool SIS Help site. |
School |
|
Jul 2003 |
Final check of school setup and implementation. |
Implementation manager confirms all things are in order for recommendation to Training. Implementation manager sends confirmation that process is complete and that the school may request training. |
Apple/PowerSchool |
|
Jul 2003 |
Request training. |
Submit request for training to Apple/PowerSchool Training department. |
School |
|
Aug 1 2003 |
Fundamentals Training. |
Apple/PowerSchool trains school on Fundamentals with their final PowerSchool SIS data. (Apple/PowerSchool conducts initial on-site training). |
Apple/PowerSchool |
|
Aug 10 2003 |
Go live with PowerSchool SIS. |
After installation and initial training, school can begin using PowerSchool SIS. |
School |
|
Ongoing |
Address support issues. |
After school is trained, any support issues will be addressed by the Apple/PowerSchool Technical Support group. |
Apple/PowerSchool |
|
Ongoing |
Provide training. |
Based on your school's needs, Apple/PowerSchool can provide addition training. Topics include Custom Reports, Schedule Build, etc. |
Apple/PowerSchool |